Global Data Center, Novartis
Fort Worth, TX
Global Data Center, Novartis
Challenge accepted.
Engineering innovations take on an energy challenge.
Streamlined and sustainable.
As part of a company-wide strategy to streamline operations while being sustainable, Novartis constructed a new 35,000 square feet data center that could be built in phases on the existing Alcon Laboratories (a subsidiary of Novartis) campus and could be expanded over time.

Modular in design, the data halls could be built in three distinct phases. Each 10,000 square foot data hall has 1,000kW of IT power and independent mechanical and electrical systems.

Novartis challenged our design team to meet their sustainability goals while providing low total cost of ownership over the life of the building. The design team employed multiple integrated design solutions to achieve this goal. Outside, 100kW photovoltaic cell arrays generate renewable on-site power and double as shade for parking and seating areas. Harvested rainwater reduces potable water consumption, irrigates the indigenous, drought-resistant landscaping and provides water for the building's restrooms. Inside, low voltage, advanced-control LED lighting minimizes operating costs while increasing adjustability for users.

Located on a greenfield site, the project is LEED Gold certified.
/4
1
2
3
4
Results
The 35,000 square foot building will be constructed in three phases.
Rainwater harvesting provides irrigation for landscaping and graywater for building use, saving an estimated 23,000+ gallons of potable water each year.
A 100kW array of photovoltaic cells generate renewable on-site energy.
Average annual PUE is 1.20.
Engineering innovations take on an energy challenge.
Global Data Center, Novartis
Fort Worth, TX
PROJECT DATA

LEED Gold

2016